IAM 3.0

2%

Status

In Process [In Process]

2% complete, updated on Tue 9/15/26 4:16 PM by Amy Simon

Changed Status from New to In Process.
Changed Percent Complete from 0% to 2%.
Changed Health from None - No health has been set to Green - On track.
Met with IT teams to start the inventory process

Details

Dates
Mon 8/24/26 - Tue 12/29/26
Acct/Dept
Information Technology Services
Type
Projects, Enhancements and Automation / University Wide Project
Health
Green - On track
Requirements
LDAP inventory
Shared Devices
No X drive (Communication) - No Student
All ITS moved to @minnstate.edu
Communications
Created
Tue 9/15/26 4:13 PM
Modified
Tue 9/15/26 5:39 PM

Description

Roll out of Okta via the System Office project to SCSU campus by end of December 2026.

Manager

Alternate Manager(s)